Electrical Load Schedule per NEC Article 220
A load schedule is the master ledger of an electrical system — every circuit, every load, every ampere accounted for. It is the foundation from which all other electrical design flows: conductor sizing, breaker selection, transformer kVA, generator sizing, and service entrance calculations. A poorly prepared load schedule cascades into undersized equipment, tripped breakers, overloaded transformers, and code violations. NEC Article 220 provides the methods for calculating branch circuit, feeder, and service loads, including mandatory demand factor application.
NEC 220 provides two methods for residential load calculation: the Standard Method (Parts I-IV) and the Optional Method (Part V, Section 220.82). The Standard Method requires itemizing all loads by category — general lighting (Table 220.12 at 3 VA/ft²), small appliance circuits (2 × 1,500 VA per 220.52(A)), laundry circuit (1,500 VA per 220.52(B)), fixed appliances (nameplate rating), motors (125% of largest motor FLC per 430.24), HVAC (larger of heating or cooling per 220.60), and applying specific demand factors for each category. The Optional Method provides a simplified calculation for dwelling units: first 10 kVA at 100%, remainder at 40% — but requires the dwelling to have electric cooking or space heating.
Commercial load calculations follow NEC 220.12 for general lighting (VA per square foot by occupancy type), NEC 220.14 for receptacles, and NEC 220.44 for receptacle demand factors. A critical difference from residential: commercial receptacle loads get their own demand factor calculation — first 10 kVA at 100%, remainder at 50% (NEC 220.44). Motor loads must use the largest motor at 125% plus all others at 100% (NEC 430.24). The continuous load multiplier of 125% per NEC 215.2(A)(1) applies to any load expected to operate for 3+ hours.
NEC demand factors recognize that not all loads operate simultaneously. Key demand factor tables: NEC Table 220.42 for general lighting (first 3,000 VA at 100%, next 3,001-120,000 VA at 35%, remainder at 25% for dwellings). NEC Table 220.54 for electric dryers (first 4 at 100%, 5th at 80%, 6th at 70%... down to 25% for 23+ units). NEC Table 220.55 for cooking equipment (column B and column C provide demand factors by number of appliances — 12 ranges at 8 kW demand each instead of 12 × 12 kW = 144 kW). NEC Table 220.56 for kitchen equipment in commercial facilities.
Panel scheduling — the physical layout of circuits within a panelboard — is an engineering discipline beyond simply assigning breaker slots. Phase balance requires distributing single-phase loads evenly across the three phases (A-B-C) so that neutral current is minimized. Maximum imbalance is typically limited to 10-15% between phases. Circuit grouping should co-locate related loads (e.g., all kitchen circuits on adjacent breakers) for operational clarity. Spare capacity planning: ANSI/NECA 1 recommends 20-25% spare breaker positions and 15-20% spare capacity in feeders for future additions. Over-filling a panel leaves no room for tenant improvements or technology upgrades.
Load schedule documentation should include: circuit number, breaker size (A), wire size, conduit/raceway reference, connected load (VA and A), demand load (VA), phase assignment (A/B/C), and load description. The schedule calculates total connected load, total demanded load, and phase balance. For multi-panel facilities, a feeder schedule rolls up panel totals to distribution boards, and distribution board totals roll up to the main switchgear and service entrance. Each level applies its own demand factors per NEC 220. This hierarchical approach prevents double-dipping demand factors — a mistake that undersizes upstream equipment.