Advanced5 steps

Data Center Power Distribution Design

Design power distribution for a small data center — transformer sizing, UPS, PDU layout, and redundancy calculations.

Scenario Overview

Design the power distribution for a 200 kW IT load data center with 2N redundancy, including transformer, UPS, and PDU sizing. This is a Tier II facility with a single utility feed and UPS backup.

Given Information

  • IT load: 200 kW (planned maximum)
  • Redundancy: 2N UPS, N+1 cooling
  • Utility feed: 480V, 3-phase from building main
  • IT voltage: 208Y/120V for server racks
  • PUE target: 1.4 (total facility power/IT load)
  • Generator backup: yes, 10s transfer

Calculation Steps

1

Determine Total Facility Power

PUE = Total Facility Power / IT Load.

Total = 200 kW × 1.4 PUE = 280 kW.

Non-IT loads (cooling, lighting, losses): 280 − 200 = 80 kW.

200 kW × 1.4 PUE = 280 kW total

Result: 280 kW total facility power

2

Size Main Transformer

Total: 280 kW at approximately 0.90 PF = 311 kVA.

Select next standard size: 500 kVA, 480V to 208Y/120V.

This provides 64% loading — excellent for efficiency and growth.

Secondary FLA: 500,000 / (208 × √3) = 1,388A.

280 kW / 0.90 PF = 311 kVA → 500 kVA transformer

Result: 500 kVA transformer (64% loaded)

3

Size UPS System (2N Redundancy)

2N means two independent UPS systems, each sized to carry 100% of IT load.

Each UPS: 200 kW at 0.90 PF = 222 kVA minimum.

Select: 2× 250 kVA UPS units (each at 89% loading).

Battery runtime: 10 minutes minimum (bridging to generator start).

Result: 2× 250 kVA UPS units (2N redundancy)

4

PDU Distribution

200 kW across standard 42U racks: approximately 5-8 kW per rack.

25-40 racks at 5-8 kW each.

PDU: whip-style 30A or 50A, 208V PDUs to each rack.

Main PDU panels: 2× 400A, 208Y/120V panels (one per UPS output).

Result: 2× 400A PDU panels, 25-40 rack PDUs

5

Generator Sizing

Total facility: 280 kW.

Generator sizing: 280 kW / 0.80 loading = 350 kW minimum.

Motor starting factor: HVAC compressors may need 2× starting kVA.

Select: 500 kW diesel generator (provides growth headroom).

Fuel: NEC 700.12(B)(2) requires 2 hours minimum; NFPA 110 recommends 24-48 hours.

280 kW / 0.80 = 350 kW → 500 kW generator

Result: 500 kW diesel generator

Final Answer

200 kW IT data center with 2N UPS (2× 250 kVA), 500 kVA transformer (480 to 208Y/120V), 500 kW generator, and 2× 400A PDU panels. Total facility power: 280 kW at PUE 1.4. Full redundancy from UPS to rack PDU.

Key Takeaways

  • PUE accounts for ALL facility power — cooling is typically 30-40% of non-IT load
  • 2N redundancy means each UPS must carry 100% of load independently
  • Transformers for data centers should be K-13 or K-20 rated for harmonic loads
  • Generator must account for motor starting surge of HVAC compressors

Calculators Used

NEC References

  • NEC 645 — Information Technology Equipment
  • NEC 700/701 — Emergency/Standby Systems
  • NEC 450 — Transformers
  • TIA-942 — Data Center Standards

Project Explorer

No Projects Found