What Size Wire for 100 Amps at 200 Feet?
- Load
- 100 A
- Distance
- 200 ft
- Band
- 100 A feeder
- Defaults
- Non-continuous, 75 C lugs, 86 F, 240 V single-phase
Computed Starting Point
Ampacity and voltage drop under common defaults for this amp and distance.
| Material | Computed size | OCPD | Usable ampacity | Governing constraint | Default check |
|---|---|---|---|---|---|
| Copper | 1 AWG | 100 A | 130 A | Voltage drop | Passes defaults |
| Aluminum | 2/0 AWG | 100 A | 135 A | Voltage drop | Passes defaults |
What 200 ft ChangesAt 200 ft, voltage drop is no longer a borderline caveat. It governs the default result for both materials, and the adjacent 250 ft page jumps again. Before buying conductor, compare the cost of upsizing with equipment placement, subpanel location and the actual load current that will flow for long periods.
Zero-Length vs This Distance
If the distance-adjusted size is larger, voltage drop governed under these defaults.
| Case | Copper size | Copper constraint | Aluminum size | Aluminum constraint |
|---|---|---|---|---|
| Ampacity only (0 ft) | 3 AWG | Termination rated 75 C | 1 AWG | Termination rated 75 C |
| 200 ft (this page) | 1 AWG | Voltage drop | 2/0 AWG | Voltage drop |
Adjacent Distances at This Amp
Neighboring published lengths for 100 A under the same defaults.
| Distance | Copper size | Aluminum size | Copper constraint |
|---|---|---|---|
| 150 ft | 2 AWG | 1/0 AWG | Voltage drop |
| 200 ft (this page) | 1 AWG | 2/0 AWG | Voltage drop |
| 250 ft | 1/0 AWG | 3/0 AWG | Voltage drop |
200 ft Is a Long Detached-Building Feeder
100 A feeder context for 100 A at 200 ft.
A 200 ft 100 A run is usually past the quick garage-panel question and into a real feeder layout: detached shop, long driveway, outbuilding, or equipment pad where conductor cost and raceway size are part of the decision.
Compared with the zero-length result, both materials have moved two common size steps under these defaults. That is why this page should read like a long-run planning page, not a generic 100 A ampacity chart.
What Changes This Long-Run Answer
Checks that matter for distance-governed sizing in this amp band.
Price raceway and lugs with the conductor
The 200 ft answer uses physically larger conductors than the short-run 100 A result. Confirm raceway fill, bend space and equipment lug acceptance before ordering.
Consider equipment placement
Moving a subpanel or load center closer to the load can sometimes cost less than carrying the full 100 A load across the entire 200 ft route.
Check the 250 ft cliff
If the route is not final, do not buy from the 200 ft row alone. The next published distance requires another upsize under the same defaults.
Keep service size separate
This page assumes 100 A is the correct feeder rating. A load calculation still owns whether 100 A is enough for the building or equipment served.